Blaise Alexander Ford

Location: Lewisburg, Pa

This project was located at Blaise Alexander Ford on route 45 in Lewisburg Pa. This project included demo and land clearing along with cut and fill for new parking areas. We tied into the sanitary sewer from the new show room and grease trap. With the new parking, we had to extend the existing sanitary man hole up to grade. Rock lined slopes behind much of the parking were installed along with gabion baskets as well. Storm water inlets and piping were installed including two underground basins and a rain garden. These basins were constructed by cutting to subgrade, adding geotec fabric and crushed stone followed by the inlets and piping. We also trenched and augured for the light standards in the parking areas. 2A stone was used to prep for curb and pavement subgrade.